SUBJECT:
Title
Request Approval of a State of Florida Department of Transportation State Funded Grant Agreement and Resolution for the SW 80th Avenue, Segment 2 Widening Project (FPN 457555-2-34/44-01) (Budget Impact - Neutral; reimbursement of up to $1,300,000)
Body
|
INITIATOR: |
DEPARTMENT: |
|
Steven Cohoon, P.E., County Engineer |
Office of the County Engineer |
DESCRIPTION/BACKGROUND:
The State of Florida Department of Transportation (FDOT) has awarded a State Funded Grant Agreement (SFGA) for the SW 80th Avenue, Segment 2 Widening Project, from 1/2 mile north of SW 38th Street to W Highway 40 (FPN 457555-2-34/44-01). Receipt of the grant requires execution of the agreement and the supporting Resolution.
The SFGA is for the design phase (Phase 34) and right-of-way (ROW) acquisition phase (Phase 44) of the project. Currently, the design phase is 60% complete. Prior design phase expenditures will be ineligible for reimbursement; design phase expenditures incurred after the execution of this Agreement will be eligible for reimbursement. The ROW acquisition phase will begin upon execution of this Agreement with all expenditures being eligible for reimbursement.
BUDGET/IMPACT:
Neutral; reimbursement of up to $1,300,000.
RECOMMENDED ACTION:
Recommended action
Motion to approve and authorize the Chairman and Clerk to execute the attached State Funded Grant Agreement and Resolution.