File #: 2024-16225   
Type: Project Adjustment Status: Agenda Ready
File created: 8/13/2024 Meeting Body Board of County Commissioners
On agenda: 8/20/2024 Final action:
Title: Transfer Project Funds and Amend the Capital Improvement Program - Infrastructure Surtax Capital Project Fund - $226,452
Attachments: 1. Agenda Changes STC073812, STC073876 and STC073877, 2. STC073876 Project Close Out Form 08-09-24

 

SUBJECT:

Title

Transfer Project Funds and Amend the Capital Improvement Program - Infrastructure Surtax Capital Project Fund - $226,452

Body

 

INITIATOR:

DEPARTMENT:

Michael McCain, Executive Director

County Administrator

 

DESCRIPTION/BACKGROUND:

This BAR serves to close out project STC073876 - SW 31st St/SW 34th Pl Infrastructure Surtax. Resurfacing is complete and final invoices have been paid. The project saved $191,545 against its original budget. This balance will be transferred to STC073877 - NW 60th Ave Resurfacing as it requires an increase in funding to begin construction.

 

Additionally, $34,907 will be transferred from STC073812 - NW 80th Ave/NW 70th Ave to STC073877, as this project is still pending ROW acquisition before construction can begin. This funding can be replaced at a later date.

 

BUDGET/IMPACT:

Neutral

 

RECOMMENDED ACTION:

Recommended action

Motion to approve the transfer of project funds and amend the Capital Improvement Program.