Request Approval of Task Order: 25Q-106-TO-12 Utilities Engineering Design Support Services, Southwest Regional Water Reclamation Facility Odor and Erosion Control Study - Clymer Farner Barley, Inc., Ocala, FL (Budget Impact - Neutral; expenditure of $227,684)
Body
|
INITIATOR: |
DEPARTMENT: |
|
Susan Olsen, Director |
Procurement Services |
DESCRIPTION/BACKGROUND:
On September 16, 2025, the Board approved contracts with seven (7) firms to provide Utilities Engineering Design Support Services for Marion County.
Under this agreement, Marion County Utilities (MCU) has assigned Clymer Farner Barley, Inc., to provide professional engineering services for the Southwest Regional Water Reclamation Facility Odor and Corrosion Control Study.
This work will include the evaluation of the sanitary sewer collection system and identification of potential upgrades to the collection system to mitigate public odor complaints and hydrogen sulfide induced corrosion.
A copy of the Clymer Farner Barley, Inc., proposal is attached for review and upon approval will become part of the project file and backup to the purchase order.
BUDGET/IMPACT:
Neutral; expenditure of $227,684. Funding for this project is from ZF448536-562102 (Marion County Utility Fund), Project UTC000101.
RECOMMENDED ACTION:
Recommended action
Motion to approve and allow staff to release the purchase order for Clymer Farner Barley, Inc, under 25Q-106.