Title: Request Approval of Water Main Extension Connection Agreement WME-089-O Between Alexandra Osejo and Marion County Utilities (Budget Impact - Neutral; expenditure of $30,232)
Attachments: 1. LRM - Agreement WME-089-O, 2. Agreement WME-089-O

 

SUBJECT:

Title

Request Approval of Water Main Extension Connection Agreement WME-089-O Between Alexandra Osejo and Marion County Utilities (Budget Impact - Neutral; expenditure of $30,232)

Body

 

INITIATOR:                                                                                                                              DEPARTMENT:

Tony Cunningham, P.E., Director                                          Utilities


DESCRIPTION/BACKGROUND:

In accordance with Land Development Code section 6.14.2, developers (property owners) are required to connect to public utilities if the property is within connection distance. For a single-family residence, the connection distance is 400 feet from the parcel’s closest corner to the public water main. In this case, the property owner is required to connect to the public water main provided by Marion County Utilities (MCU), which will result in installing 276 feet of water main across the parcel’s frontage to the end of the property. The water main extension project will create a benefit for four (4) additional parcels along the route.  

Total Project Cost

$ 30,232

Construction ($29,532) + Design ($700)

MCU Cost Only

-   $ 3,000

Fire hydrant assembly

Collective Owners’ obligation

$ 27,232

 

Per Parcel Cost

$ 5,446.40

Five (5) parcels

 

 

BUDGET/IMPACT:

Neutral; project cost is $30,232 and construction purchase order includes 10% contingency in accordance with the Procurement Manual.  Funding is from ZF448536-563102 with project code UTC000094

 

RECOMMENDED ACTION:

Recommended action

Motion to approve and authorize the Chairman and Clerk to execute the subject Water Main Extension Connection Agreement and authorize staff to issue the purchase order for T&C Underground under 22P-146.