SUBJECT:
Title
Request Approval of a Purchase Agreement and Addendum in Association with Future Utility Development for Parcels 35341-002-25 & 35341-001-20 (Budget Impact - Neutral; expenditure of $4,120,000)
Body
|
INITIATOR: |
DEPARTMENT: |
|
Tony Cunningham, PE, Director |
Utilities |
DESCRIPTION/BACKGROUND:
The Southwest Regional Water Reclamation Facility is currently in design to be expanded. Marion County Utilities (MCU) staff conducted a workshop with the Board on December 2nd, 2025, to discuss the plant expansion plan. In conjunction with the expansion, this land purchase will expand the plant property to include an additional 32.96 acres to the west and south of the existing plant site. The additional property will be available for expansion of plant reclaimed water facilities, utilized as a buffer from adjacent uses, utilized for relocation of some of the unit process facilities further west away from existing residents and to construct an access road to directly serve the plant site.
This is a request to approve a Purchase Agreement in the amount of $4,120,000, plus closing costs and Addendum to the Purchase Agreement for parcels 35341-002-25 and 35341-001-20 in association with future utility development. This purchase is approximately 32.96 acres.
BUDGET/IMPACT:
Neutral; expenditure of $4,120,000, plus closings costs (Fund- ZF440536 - 561101).
RECOMMENDED ACTION:
Recommended action
Motion to approve and authorize the Chairman and Clerk to execute the Purchase Agreement and Addendum.
end