Title:
|
8010-0976-02 Water Main Extension Waiver - Waiver Request to Water Main Extension
13188 SW 65th Circle Ocala
Project #2024040049 #31423 Parcel #8010-0976-02 Permit #2024021099
Dala Developments
LDC 6.14.2.A(3) - Water Main Extension to Farthest Property Corner
CODE states When property is within connection distance to water, the water main shall be extended to the farthest property line by Developer. Refer to Sec. 6.15.3.B for fire hydrant installation requirements.
APPLICANT states Water main exists at parcel's lot line but not across as is required by Code. CONDITIONAL WAIVER approved provided applicant (1) opens a water utility account with MCU; (2) pays all Connection charges; and (3) pays $5K capital connection fee as this is part of a pending ARPA grant to design and extend water main for all gaps in Marion Oaks Units 7/10.
|