Title: Request Approval of a Florida Department of Transportation State - Funded Grant Supplemental Agreement and Resolution for Construction of the Proposed Dunnellon Trail Project in Marion County (Budget Impact - Decrease; reduction in grant and estimated expenditures by $589,417)
Attachments: 1. LRM-SFGA SA#1-signed, 2. Supplemental Grant Agreement, 3. Resolution, 4. EXECUTED State-Funded Grant Agreement, 5. Dunnellon Trail Project City Letter, 6. MAP

 

SUBJECT:

Title

Request Approval of a Florida Department of Transportation State - Funded Grant Supplemental Agreement and Resolution for Construction of the Proposed Dunnellon Trail Project in Marion County (Budget Impact - Decrease; reduction in grant and estimated expenditures by $589,417)

Body

 

INITIATOR:

DEPARTMENT:

Steven Cohoon, P.E., County Engineer

Office of the County Engineer

 

DESCRIPTION/BACKGROUND:

The County previously entered into a State-Funded Grant Agreement with the Florida Department of Transportation (FDOT), for Grant Agreement Contract Number G2L16 FPN 450918-1-54-01, also known as the Dunnellon Trail Project, on behalf of the City of Dunnellon.

 

At the May 21, 2024 meeting of the Marion County Board of County Commissioners (BCC), a letter from the City of Dunnellon was presented for notation, formally requesting the termination of the Dunnellon Trail Project. The project, identified by FDOT Financial Project Numbers 450918-1-34-01 (design) and 450918-1-54-01 (construction), was originally planned to enhance regional trail connectivity and recreational opportunities. However, the City cited feasibility concerns and a reassessment of the project's overall benefit as reasons for seeking its cancellation.

 

This Supplemental Agreement (SA) reflects the reduction of Construction Funding in the amount of ($589,417.00) resulting from the reduced Scope of Work. The revised Supplemental Grant Agreement Amount is $2,162,000.00. The limits of the project are 50 feet west of Adams Street to the Blue Run of Dunnellon Park, along CR 484 (aka Pennsylvania Avenue), for a total length of approximately 0.12 miles. However, the multi-use trail limits are reduced to a pedestrian crossing along the CR 484 bridge, connecting to Blue Run Park.  The overall project limits will provide for three (3) crosswalks, including midblock crossings with Rectangular Rapid Flashing Beacons (RRFBs).

 

BUDGET/IMPACT:

Decrease; reduction in grant and estimated project expenditures by $589,417.

 

RECOMMENDED ACTION:

Recommended action

Motion to approve the attached Supplemental Grant Agreement and Resolution, and authorize the Chairman and Clerk to execute the same.

end