SUBJECT:
Title
Infrastructure Surtax Capital Project Fund - Infrastructure Tax Transportation - $586,368
Body
INITIATOR:
DEPARTMENT:
Steven Cohoon, P.E., County Engineer
Office of the County Engineer
DESCRIPTION/BACKGROUND:
This adjustment shifts funding in a number of Transportation Infrastructure Surtax projects. Marion Oaks Manor Extension and NE 35th St Ph 2 (from NE Jacksonville Rd to NE 25th Ave) require increases for upcoming design change orders. NE 35th St Ph 4 (from NE 36th Ave to E Silver Springs Blvd) requires an increase for an upcoming property acquisition. Additionally, in order to facilitate billing staff time to multiple projects, increases need to be made to those that have either insufficient or no budget assigned.
BUDGET/IMPACT:
Neutral
RECOMMENDED ACTION:
Recommended action
Approve attached Budget Amendment Resolution and amend the CIP.
end