File #: 2025-17921   
Type: Consent Status: Agenda Ready
File created: 1/23/2025 Meeting Body Board of County Commissioners
On agenda: 2/4/2025 Final action:
Title: Request Approval of Water Main Extension Connection Agreement WME-081-O Between Roberto DeFreitas and Marion County Utilities (Budget Impact - Neutral; expenditure of $14,326)
Attachments: 1. LRM - Agreement WME-081-O, 2. Agreement WME-081 -O

 

SUBJECT:

Title

Request Approval of Water Main Extension Connection Agreement WME-081-O Between Roberto DeFreitas and Marion County Utilities (Budget Impact - Neutral; expenditure of $14,326)

Body

 

INITIATOR:                                                                                                                              DEPARTMENT:

Tony Cunningham, P.E., Director                                          Utilities


DESCRIPTION/BACKGROUND:

In accordance with Land Development Code section 6.14.2, developers (property owners) are required to connect to public utilities if the property is within connection distance. For a single-family residence, the connection distance is 400 feet from the parcel’s closest corner to the public water main. In this case, the property owner is required to connect to the public water main provided by Marion County Utilities (MCU) and is required to install 71 feet of water main across the parcel’s frontage to the end of the property. The water main extension will serve the property owner’s parcel only.  Total project cost is derived from the construction cost ($13,625.50) plus design fee ($700).

 

BUDGET/IMPACT:

Neutral; project cost is $14,325.50 and construction purchase order includes 10% contingency in accordance with the Procurement Manual.  Funding is from ZF448536-563102 with project code UTC000094.

 

RECOMMENDED ACTION:

Recommended action

Motion to approve and authorize the Chairman and Clerk to execute the subject Water Main Extension Connection Agreement and authorize staff to issue the purchase order for T&C Underground under 22P-146.