DESCRIPTION/BACKGROUND:
On April 17, 2007, the Board awarded a contract to Guerra Development Corp. for engineering and design services for various roadway projects. On March 16, 2021, the Board approved the second task order to provide professional services and assistance with the construction plans of Phase 3A and 3B of the NW 49th/35th Street Corridor project, from NW Highway 225A to NW 44th Avenue, west of the new I-75 interchange.
Change Orders 1 through 7 added time to the contract, changed the work from a 2-lane to a 4-lane design, added design services for the evaluation and potential design of a roundabout, increased funding for the additional work, and transferred money from different line items.
This Change Order provides additional engineering services including supplemental drainage analysis, the design of pavement bulb-outs to accommodate U-turn movements for vehicles towing horse trailers, and relocation of the proposed roundabout at NW 49th Street and NW Highway 225A to reduce right-of-way acquisition impacts. The additional work includes roadway alignment revisions, drainage and permitting modifications, updated construction plans, and preparation of parcel sketches and legal descriptions to support the revised design.
The Change Order, Scope of Services, and Fee Breakdown Table are attached for review. Upon approval at today’s meeting, the Change Order will be presented to the Chairman for signature.
BUDGET/IMPACT:
Neutral; additional expenditure of $102,292 for a total project cost of $1,152,609.42. Funding comes from BO762541-563101-TIP60800F (2nd Local Option Fuel Tax), VJ738541-563220-STC073811 (Infrastructure Surtax Capital Project Fund), and GB772541-563512-TIP60800F (Impact Fee West District).
RECOMMENDED ACTION:
Recommended action
Motion to approve, allow staff to process, and authorize the Chairman and Clerk to execute Change Order 8 to Purchase Order 2100770.