Title:
|
Baseline Road Industrial - Waiver Request to Major Site Plan in Review
6259 SE 78th St Ocala
Project #2024050052 #32452 Parcel #37490-000-00
Kimley-Horn & Associates
This item was tabled by DRC on 3/31/25 and 4/7/25. This is a request to be reheard.
LDC 6.13.6.A(3)(c) - Stormwater Quality Criteria
CODE states Dry retention systems that have a depth of six feet or less, measured from top of bank to pond bottom, with side slopes that are no steeper than 4:1 and sodded bottoms.
APPLICANT requests waiver to allow a stormwater pond depth of 7.5 feet. Similar pond depths have been approved on like-use projects in the County. Geotechnical borings do not indicate karst features area present in the pond excavation.
|