Title:
|
CMH INC - Waiver Request to Water Connection
4000 SE 56th Ter Ocala
Project #2024080046 #31887
Parcel #3137-004-022 Permit #2024053482
Ellamia, LLC
LDC 6.14.2.B(1)(a) - Water Connection
CODE states New development in the Urban or Rural area shall connect to a centralized water system with available capacity if a water line is within a connection distance of 400 feet times the total number of Equivalent Residential Connections (ERCs).
APPLICANT requests waiver because the property has existing well. New water main (which is 400 feet away) will cost $50,000 and take one year to complete. The cost for city water to be brought to homesite is way too expensive. The estimate is 48 to 55K. The timeline from MCU is 10 to 12 months which is too long for this home project. I did get an independent bid from Civil Works & Maintenance LLC and this estimate is almost $45K which is way too much also for our home project. This lot already has a working well and septic and if we have ...
|