SUBJECT:
Title
Transfer Project Funds and Amend the Capital Improvement Program - General Fund - $185,101
Body
INITIATOR: DEPARTMENT:
Jared Goodspeed, Director Facilities Management
DESCRIPTION/BACKGROUND:
Facilities Management is requesting a one-time transfer of project funds from FMC000020 (JC2 Replacement of Air Handlers) to SAC000001 (JC3 4th Floor Expansion). Both of these projects are courthouse capital improvements. FMC000020 is in the final stages of completion and will not be utilizing the remaining $185,101 where as SAC000001 is in need of additional funds in order to have contingency on the project.
BUDGET/IMPACT:
Neutral
RECOMMENDED ACTION:
Recommended action
Motion to approve the transfer of project funds and amend the CIP.
end