Title:
|
Freedom Park Commercial & Professional Center – Major Site Plan 000719-2026 – Waiver Request to Turn Lanes
Parcel#: 35699-006-03 #WaiverPIR-001593-2026
Tillman & Associates Engineering, LLC
LDC 6.12.11 - Turn lanes
CODE states Turn lanes shall be required as warranted by the project's Traffic Impact Analysis and in accordance with FDOT or as approved by the County Engineer. In addition, turn lanes shall be considered any time an unsafe condition exists or will be created. The cost of construction of such lanes shall be the responsibility of the developer. Additional right-of-way may be required and shall be dedicated by the developer and shown on the Improvement Plans and Final Plat. Any off-site improvement designs shall be submitted as an Improvement Plan application.
APPLICANT Requests to allow the proposed SW 60th Avenue right-turn lane to be reviewed and approved as part of this Major Site Plan. Submittal promotes economic flexibility in that a different plan set wouldn’t nee...
|