File #: 2025-18270   
Type: Budget Amendment Status: Agenda Ready
File created: 2/20/2025 Meeting Body Board of County Commissioners
On agenda: 3/5/2025 Final action:
Title: Stormwater Fund - Stormwater Program - $773,878
Attachments: 1. 2025-6-8 $773,878

 

SUBJECT:

Title

Stormwater Fund - Stormwater Program - $773,878

Body

 

INITIATOR:

DEPARTMENT:

Steven Cohoon, County Engineer

Office of the County Engineer

 

DESCRIPTION/BACKGROUND:

Project SMC0008WQ - NW 44th Ave Innovative Stormwater Retrofit is being closed. The project was deemed unfeasible due to the capacity limitations of the existing drainage retention area. Florida Department of Environmental Protection (FDEP) grant agreement LPS0100 was terminated at the County's request on September 23, 2024. This adjustment removes the grant funding in the amount of $337,381, and transfers remaining funding in the amount of $436,497 to SMC0001MA - SE Timucuan Rd Culvert Replacement, as additional funding is needed in that project to begin construction.

 

BUDGET/IMPACT:

Decrease Stormwater Fund appropriation by $337,381

 

RECOMMENDED ACTION:

Recommended action

Approve attached Budget Amendment Resolution and amend the Capital Improvement Program.