File #: 2025-20834   
Type: Consent Status: Agenda Ready
File created: 10/2/2025 Meeting Body Board of County Commissioners
On agenda: 10/21/2025 Final action:
Title: Request Approval of Change Order 3 to Purchase Order 2500776: 25Q-002 SW 40th Ave/SW 49th Ave Phase 1 - Art Walker Construction, Inc., Ocala, FL (Budget Impact - Neutral; additional expenditure of $239,538)
Attachments: 1. CHANGE ORDER #3, 2. ART WALKER PROPOSAL, 3. 25Q-002 EC, 4. Map_SW40th-49thAve STC073804_v2.pdf

SUBJECT:

Title

Request Approval of Change Order 3 to Purchase Order 2500776: 25Q-002 SW 40th Ave/SW 49th Ave Phase 1 - Art Walker Construction, Inc., Ocala, FL (Budget Impact - Neutral; additional expenditure of $239,538)

Body

 

INITIATOR:

DEPARTMENT:

Susan Olsen, Director

Procurement Services

 

DESCRIPTION/BACKGROUND:

On December 17, 2024, the Board approved a contract with Art Walker Construction, Inc., for a design-build project. The work includes completing the existing 90% design plans and constructing Phase 1 of the SW 40th Ave/SW 49th Ave Corridor (SW 66th St to SW 43rd Street Rd). Purchase Order (PO) 2500776 was issued for the work, totaling $16,889,149.20.

 

Throughout the term of the project, Change Order 1 was released to add $2,195,280.22 to cover the construction of new gravity sewer mains in 8-inch, 10-inch, and 12-inch diameters; relocating an existing sewage pump station; installation of a new 16-inch water main; adjustment of select valve boxes and manhole covers; relocating fire hydrant assemblies on existing water mains; relocating an existing water main; and relocating a section of the existing 6-inch force main along S.R. 200.

 

Change Order 2 was released to add $875,112 to cover tasks needed to continue the project as specified in the proposal from Art Walker Construction, Inc. Task A: Design, permitting and construction for site improvement for SPX Flow property; Task B: Median revisions and construction along SW 40th/49th Ave; Task C: Design plan modification for SW 66th St at SW 49th Ave intersection; Task D: Re-design pond B-2 to eliminate joint use conditions; Task E: Assistance to County Attorney’s Office for eminent domain support; Task F: Provide update to County’s Preliminary Engineering Report (PER) for Pond B-2 Re-Design. These changes were required to address the outcomes of right-of-way negotiations and eminent domain proceedings, while maintaining project continuity and minimizing potential legal costs.

 

Change Order 3 requests to add $239,537.25 to cover tasks A-E needed to continue the project as specified in the proposal from Art Walker Construction, Inc. Task A: SW 66th St and SW 49th Ave intersection lighting design and construction coordination; Task B: Gravity wall addition to SW 40th/49th Ave design and construction; Task C: Revise drainage design to eliminate and revise plans further for pond B-2 design and coordination; Task D: Right of way staking-clearing for power relocation; E: Surface depression remediation.

 

Attached for review is a copy of Change Order 3 and the Proposal by Art Walker Construction, Inc. Upon approval at today’s meeting, the Change Order will be presented to the Chairman and the Clerk for signature.

BUDGET/IMPACT:

Neutral; additional expenditure of $239,537 bringing the project’s total cost to $20,199,078.67. Funding is available in line GB772541-563512 (Impact Fee - West District).

 

RECOMMENDED ACTION:

Recommended action

Motion to approve, authorize the Chairman and Clerk to execute, and allow staff to process Change Order 3 to Purchase Order 2500776 for Art Walker Construction, Inc. under 25Q-002.

 