File #: 2026-22201   
Type: Consent Status: Agenda Ready
File created: 2/26/2026 Meeting Body Board of County Commissioners
On agenda: 3/17/2026 Final action:
Title: Request Approval of Change Orders to Purchase Order 2401106: 23Q-225 CR 475A (SW 27th Avenue) Improvements - Kittelson & Associates, Inc., Orlando, FL (Budget Impact - Neutral; additional expenditure of $261,826)
Attachments: 1. 23Q-225 CO4 PO 2401106, 2. 23Q-225 Exhibit B Optional Task, 3. 23Q-225 CO4 Map SW 27th Ave Elevated Two Lane Roadway.pdf, 4. 23Q-225 CO5 PO 2401106, 5. 23Q-225 CO5 Map Intersection

SUBJECT:

Title

Request Approval of Change Orders to Purchase Order 2401106: 23Q-225 CR 475A (SW 27th Avenue) Improvements - Kittelson & Associates, Inc., Orlando, FL (Budget Impact - Neutral; additional expenditure of $261,826)

Body

 

INITIATOR:

DEPARTMENT:

Susan Olsen, Director

Procurement Services

 

DESCRIPTION/BACKGROUND:

On February 20, 2024, the Board of County Commissioners (BCC) approved a Request for Qualifications (RFQ) and awarded a contract to Kittelson & Associates, Inc. to design and prepare construction plans for elevating CR 475A (aka SW 27th Avenue) from 0.7 miles north of SW 66th Street to SW 42nd Street and to conduct an intersection study, analysis, design, and provide construction plans for CR 475A at SW 66th Street. The RFQ also provided for future work including the preparation of a Preliminary Engineering Report (PER) for the CR 475A four-lane widening project, and all documents associated with the work.

Change Order 4:

During the design process of the elevated roadway portion of the project, the need for a Pumping Analysis was identified. This work was included in the original contract as an Optional Task under Exhibit B - Fee Schedule, Task A.

The Pumping Analysis will:

                     Estimate expected stormwater runoff and potential flood impact in a storm event

                     Evaluate the performance and impact of the existing Drainage Retention Area (DRA)

                     Analyze potential pumping scenarios and recommend an appropriate pump selection

                     Develop recommended operating procedures for pumping operations

Change Order 5:

It was determined that a PER for the intersection of CR 475A and SW 66th Street was needed for this portion of the project. This work was not included in the RFQ scope and is separate from the future CR 475A four-lane widening PER. This PER will evaluate alternative intersection improvements to enhance operations and safety with the following:

                     Analyze traffic operations and safety conditions

                     Evaluate improvement alternatives

                     Provide concept plans

                     Develop cost estimates

                     Identify right-of-way impacts

                     Conduct public involvement activities

                     Prepare and finalize the PER

The Change Orders, exhibits, and maps are attached for review. Upon approval at today’s meeting, the Change Orders will be presented to the Chairman for signature.

 

BUDGET/IMPACT:

Neutral;

Change Order 4 additional expenditure $113,360;

Change Order 5 additional expenditure $148,466;

Total additional expenditure $261,826;

Funding comes from BM761541-563221 (80% Gast Tax Construction Fund).

 

RECOMMENDED ACTION:

Recommended action

Motion to approve, allow staff to process, and authorize the Chairman and Clerk to execute Change Orders 4 and 5 to Purchase Order 2401106.