Skip to main content
File #: 2026-21777   
Type: Consent Status: Agenda Ready
File created: 1/8/2026 Meeting Body Board of County Commissioners
On agenda: 1/20/2026 Final action:
Title: Request Acceptance of Dunnellon Oaks Improvement Area into Warranty Period and for County Maintenance (Budget Impact - None)
Attachments: 1. Engineer Letter of Acceptance, 2. BCC Start Warranty Letter - Zalak, 3. Dunnellon Oaks Plat Map F-124 - Public Dedication 07-13-1969, 4. Location Maps - Dunnellon Oaks

 

SUBJECT:

Title

Request Acceptance of Dunnellon Oaks Improvement Area into Warranty Period and for County Maintenance (Budget Impact - None)

Body

 

INITIATOR:

DEPARTMENT:

Chad Wicker, Director

Municipal Services

 

DESCRIPTION/BACKGROUND:

The following road improvement project has been completed and constructed according to plan.  In accordance with the contract, this project is under a warranty period of one (1) year. The Dunnellon Oaks Subdivision, as recorded in plat book F, page 124 and page 124A dedicate said lands and plat for the uses and purposes therein expressed and dedicated the streets, alleys, thoroughfares, parks, and easements shown hereon to the perpetual use of the Public.  The Board accepts the roads, drainage facilities and appurtenances included with the assessment project. This improvement area will be maintained by the Office of the County Engineer after the Warranty period has ended.

 

PROJECT

BID

ENGINEER

CONTRACTOR

DATE COMPLETED

Dunnellon Oaks

24B-245

Tillman & Associates Engineering, LLC

Counts Construction Co., Inc.

09/04/2025

 

 

BUDGET/IMPACT:

None

 

RECOMMENDED ACTION:

Recommended action

Motion to accept maintenance of the Dunnellon Oaks Improvement Area, and to accept construction of Dunnellon Oaks Improvement Area and authorize Chairman to execute letter advising the contractor of the one (1) year warranty period.

end