Diamond A Shopping Center - Major Site Plan - Waiver to Major Site Plan in Review
Project #2025100091 #33554
Parcel # 41200-056-04; 41200-056-12 and portion of 41200-056-00
Tillman & Associates Engineering, LLC
LDC 2.1.3 - Order of Plan Approval
CODE states Plans listed below may be reviewed concurrently, but must be approved in the order listed below, when applicable and when the proper land use and zoning are in place: A. Master Plan. B. Preliminary Plat. C. Improvement Plan. D. Final Plat. E. Major Site Plan. However, a Major Site Plan can be substituted for the Improvement Plan and can be approved before approval of the Final Plat in cases when the infrastructure improvements supporting the plat are proposed as part of the Major Site Plan application.
APPLICANT requests a waiver to allow for current approved Improvement Plan (AR #31954) to act as Major Site Plan which will allow owner to pull building permits at their own risk. A hold will be placed on all COs until major site is approved.