Request Approval of a Purchase Agreement Associated with the SW/NW 80th/70th Avenue Segment 3 Road Project for a Portion of Parcel 21625-000-02 (Budget Impact- Neutral; expenditure of $6,100)
Body
|
INITIATOR: |
DEPARTMENT: |
|
Steven Cohoon, P.E., County Engineer |
Office of the County Engineer |
DESCRIPTION/BACKGROUND:
This is a request to approve a Purchase Agreement in the amount of $6,100 plus closing costs for a portion of parcel 21625-000-02 associated with the SW/NW 80th/70th Avenue Segment 3 Road Project (from +/- 900 feet north of SR 40 to +/- 600 feet south of US Hwy 27). This is a Fee Simple taking of approximately 0.007 acres and a Temporary Construction Easement (TCE) of 0.018 acres.
The negotiated agreement is inclusive of any and all costs associated with this transaction. There are cost savings in this negotiation by avoiding additional costs that occur during condemnation proceedings.
BUDGET/IMPACT:
Neutral; expenditure of $6,100 plus closing cost ($4,100 for right-of-way from fund STC073812-CIPTRANSP-EXPANSROW-738-VJ738541-561301 and $2,000 for the TCE from fund STC073812-STC073812-EXPANS CNS-738-VJ738541-563220)
RECOMMENDED ACTION:
Recommended action
Motion to approve and authorize the Chairman and Clerk to execute the Purchase Agreement.