SUBJECT:
Title
Request Approval of the Release of a Subdivision Improvement Agreement with Letter of Credit Associated with McGinley Landing Phase 1 (renamed to 1a) (Budget Impact - None)
Body
INITIATOR:
DEPARTMENT:
Steven Cohoon, P.E. County Engineer
Office of the County Engineer
DESCRIPTION/BACKGROUND:
This is a request to approve the Release of a Subdivision Improvement Agreement with Letter of Credit associated with McGinley Landing Phase 1 (renamed to 1a). The improvements were inspected on May 9, 2025 and a Certification of Satisfactory Completion letter was sent to the Developer. The release will be recorded in the Public Record for proper satisfaction of the surety bond.
BUDGET/IMPACT:
None
RECOMMENDED ACTION:
Recommended action
Motion to approve the attached Release and to authorize the Chairman and Clerk to execute the same.
end