Belleview Circle K - Major Site Plan - 33483 - Waiver to Major Site Plan in Review
Parcel #: 45415-000-00, 45415-002-00 #WaiverPIR-000872-2026
Cadjazz Engineering
LDC 2.12.8 Current boundary and topographic survey
CODE states Current boundary and topographic survey (one foot contour intervals extending 100 feet beyond the project boundary) based upon accepted vertical datum. Surveys will be less than 12 months old and accurately reflect current site conditions, meeting standards set forth in Ch. 5J-17 FAC. Alternate topographic data may be accepted if pre-approved by the Marion County Land Surveyor.
APPLICANT requests using Marion County lidar contours along with latest survey within the areas in proximity of this parcel, we find no offsite impacts in the pre/post development conditions.
LDC 6.13.7.B(1) Geotechnical criteria
CODE states Depth. Soil test borings shall be performed to a minimum depth of 10 feet below the proposed finished grade of the bottom of all retention/detention areas or the permanent pool elevation and once the data has been obtained the hole shall be backfilled and compacted.
APPLICANT request to waive the 10-foot depth because we have one boring at 10 feet below and one boring at 7 feet below.
LDC 6.12.12.A Sidewalks
CODE states Sidewalks shall be provided in the Urban Area, Rural Activity Centers, and Specialized Commerce Districts along arterial, collector, and major local streets where these streets adjoin the project and minimally along one side of the internal streets. Sidewalks shall be constructed with all-weather surfaces and shall meet Americans with Disabilities Act, Florida Building Code, and FDOT Design Standards.
APPLICANT requests to contribute to Marion County Sidewalk Fund in lieu of construction.
LDC 2.12.16 Environmental Assessment
CODE states An Environmental Assessment for listed species and vegetative communities.
APPLICANT - requests a waiver to the Environmental Assessment. Existing development included a number of residential and commercial buildings located throughout the site including a number of wells and utility corridors. This is a developed site.