File created: 10/11/2024 Meeting Body Development Review Committee
On agenda: 10/14/2024 Final action:
Title: McGinley Landing (Phase 2) - Waiver Request to Improvement Plan in Review 5077 SW HWY 484 Ocala Project #2024040044 #31418 Parcel #41200-056-00 & 41200-056-02 Tillman & Associates Engineering LDC 2.12.5. - Project concurrency information CODE states Project Concurrency information shall be provided per Division 1.8. LDC 1.8.2.A - Concurrency Management CODE states the following facilities are subject to concurrency review and approval, consistent with ? 163.3180 FS: (1) Potable water, (2) Sanitary Sewer, (3) Solid Waste, (4) Stormwater, (5) Schools, and (6) Roadway transportation facilities. APPLICANT requests waiver to use the submitted Traffic Study based on progress made on the Developer agreement. LDC 2.1.3. - Order of plan approval CODE states Plans listed below may be reviewed concurrently, but must be approved in the order listed below, when applicable and when the proper land use and zoning are in place: A. Master Plan. B. Preliminary Plat. C. Improvement Plan. D...
Attachments: 1. 6.3 McGinley Landing (Phase 2) - Waiver Request to Improvement Plan in Review - 31418_

 

SUBJECT:

Title

McGinley Landing (Phase 2) - Waiver Request to Improvement Plan in Review

5077 SW HWY 484    Ocala 

Project #2024040044     #31418     Parcel #41200-056-00 & 41200-056-02

Tillman & Associates Engineering

 

LDC 2.12.5. - Project concurrency information

CODE states Project Concurrency information shall be provided per Division 1.8.

LDC 1.8.2.A - Concurrency Management

CODE states the following facilities are subject to concurrency review and approval, consistent with § 163.3180 FS: (1) Potable water, (2) Sanitary Sewer, (3) Solid Waste, (4) Stormwater, (5) Schools, and (6) Roadway transportation facilities.

APPLICANT requests waiver to use the submitted Traffic Study based on progress made on the Developer agreement.

 

LDC 2.1.3. - Order of plan approval

CODE states Plans listed below may be reviewed concurrently, but must be approved in the order listed below, when applicable and when the proper land use and zoning are in place: A. Master Plan. B. Preliminary Plat. C. Improvement Plan. D. Final Plat. E. Major Site Plan. However, a Major Site Plan can be substituted for the Improvement Plan and can be approved before approval of the Final Plat in cases when the infrastructure improvements supporting the plat are proposed as part of the Major Site Plan application.

APPLICANT requests waiver for the approval of the McGinley Residential Phase Preliminary Plat and Improvement Plan prior to Master Plan Approval. A Developer’s agreement addressing offsite roadway improvements is currently under review by Marion County staff. The Master Plan will be approved upon approval of the Developer’s Agreement.   

Body

 

 

end