File #: 2025-19475   
Type: Consent Status: Agenda Ready
File created: 6/12/2025 Meeting Body Board of County Commissioners
On agenda: 7/1/2025 Final action:
Title: Request Approval of Change Order 2 & 3 to Purchase Order 02401106: 23Q-225 CR 475A (SW 27th Avenue) Improvements - Kittelson & Associates, Inc., Orlando, FL (Budget Impact - Neutral; additional expenditure of $78,175)
Attachments: 1. Change Order 2, 2. Change Order 3, 3. 23Q-225 EC, 4. CR475A-Task A_Agenda Map, 5. CR475A-Task B_Agenda Map

 

SUBJECT:

Title

Request Approval of Change Order 2 & 3 to Purchase Order 02401106: 23Q-225 CR 475A (SW 27th Avenue) Improvements - Kittelson & Associates, Inc., Orlando, FL (Budget Impact - Neutral; additional expenditure of $78,175)

Body

 

INITIATOR:

DEPARTMENT:

Susan Olsen, Director

Procurement Services

 

DESCRIPTION/BACKGROUND:

On February 20, 2024, the Board awarded a contract to Kittelson & Associates, Inc. under RFQ 23Q-225 to conduct an immediate intersection study, analysis, design, and provide construction plans for CR 475A and SW 66th Street. This project also included the preparation of a Preliminary Engineering Report for the CR 475A, 4-lane widening project and all documents associated with the work. Purchase Order (PO) 02401106 was issued for the work, totaling $1,481,953.

 

Throughout the term of the project, one (1) change order has been issued. Change Order 1 corrected the coding of the purchase order lines.

 

Change Order 2 requests approval to add $56,520 to cover the costs of additional surveying, geotechnical testing, DRA soil analysis, and temporary traffic control that are necessary outside of the initial Right-of-Way due to design modifications.

 

Change Order 3 requests the approval to add $21,655 to obtain additional surveying and geotechnical information within adjacent properties.

 

Attached for review are a copy of Change Order 2 & 3 with their respective proposals. Upon approval at today’s meeting, both Change Orders will be presented to the Chairman and Clerk for signature.

 

BUDGET/IMPACT:

Neutral; additional expenditure of $78,175, bringing the project’s total cost to $1,538,473. Funding is available in BM761541-563221-TIP000023 (80% Gas Tax Const Fund).

 

RECOMMENDED ACTION:

Recommended action

Motion to approve Change Orders, authorize the Chairman to execute, and allow staff to process Change Orders 2 & 3 to Purchase Order 02401106 for Kittelson & Associates, Inc. under project 23Q-225.

end