Legislation Details

File #: 2026-25068   
Type: Consent Status: Agenda Ready
File created: 11/13/2026 Meeting Body Board of County Commissioners
On agenda: 12/1/2026 Final action:
Title: Request Approval of Task Order: 20Q-161-TO-57 Marion County Utilities – West Marion Oaks Water Operations Building Project – Cullison Wright Construction Corp, Ocala, FL Budget Impact - Neutral; expenditure of $1,516,482)
Attachments: 1. 20Q-161-TO-57 AGN CNT.pdf, 2. 20Q-161-CA-01 EC - Cullison Wright, 3. 20Q-161C EC - Cullison Wright

SUBJECT:

Title

Request Approval of Task Order: 20Q-161-TO-57 Marion County Utilities - West Marion Oaks Water Operations Building Project - Cullison Wright Construction Corp, Ocala, FL Budget Impact - Neutral; expenditure of $1,516,482)

Body

 

INITIATOR:

DEPARTMENT:

Susan Olsen, Director

Procurement Services

 

DESCRIPTION/BACKGROUND:

On April 6, 2021, the Board approved contracts with six (6) Construction Managers (CMs) to facilitate project selection based on expertise, capacity, and availability. Facilities Management has selected Cullison Wright Construction Corp. to serve as Construction Manager for the Marion County Utilities - West Marion Oaks Water Operations Building Project.

 

The project consists of two primary components: construction of a new 40' x 200' pre-engineered metal equipment storage building with a 15' eave height, including the required foundation, structural, electrical, and site work; and renovation of the existing approximately 2,400-square-foot Marion Oaks Water Operations Office and Maintenance Building.

 

The office renovation will reconfigure the existing workshop area to create two offices and a large multi-purpose room with cubicles, lockers, and countertops. Improvements will include removal of the existing overhead door and installation of a storefront system, enlargement of two rear windows, and installation of new finishes, including flooring, paint, and cabinetry. Additional work will include demolition, framing, electrical, mechanical, plumbing, drywall, ceiling, and finish work as necessary. Existing restrooms and the remaining areas of the building will generally remain unchanged.

 

Attached for review is the draft contract. Following approval by the Board, the contract will be forwarded to Cullison Wright Construction Corp. for signature. Once returned, it will be routed to Legal, the Clerk, and the Chairman for final execution.

 

BUDGET/IMPACT:

Neutral; expenditure of $1,516,482. A contingency of up to 10% may be added to the purchase order in accordance with the Procurement Manual, for a total authorized amount not to exceed $1,668,130.20. Funding is available in ZF448536-562102 (Marion County Utility Fund), Project Code UTC000402.

 

RECOMMENDED ACTION:

Recommended action

Motion to approve, authorize staff to issue the contract, and, upon approval from Legal, authorize the Chairman and Clerk to execute the contract under 20Q-161