Title: Request Approval of Amended Water Main Extension Connection Agreement WME-093-O Between Pabliny LLC and Marion County Utilities (Budget Impact - None)
Attachments: 1. AGENDA WME-093 APP LRM (rev), 2. WME-093 AMENDED Agreement, 3. WME-093 owner's UUC proposal 3, 4. WME-093-O REF ONLY

 

SUBJECT:

Title

Request Approval of Amended Water Main Extension Connection Agreement WME-093-O Between Pabliny LLC and Marion County Utilities (Budget Impact - None)

Body

 

INITIATOR:

DEPARTMENT:

Tony Cunningham, P.E., Director

Utilities

 

DESCRIPTION/BACKGROUND:

In accordance with Land Development Code section 6.14.2, developers (property owners) are required to connect to public utilities if the property being developed is within connection distance. For a single-family residence, the connection distance is 400 feet from the parcel’s closest corner to the public water main. In this case, the property owner has applied for a building permit on a parcel within the 400’ connection distance of public water main provided by Marion County Utilities (MCU) and is required to install the water main across the parcel’s frontage, ending at the farthest corner.

 

After Agreement WME-093-O was approved by the Board on July 15, 2025, the Owner was unable to proceed with its originally selected contractor. As a result, the Owner selected a new contractor who offered a lower price. This Amendment is necessary to correct the resulting benefiting-lot payback share obligation as recorded in the Official Records.

 

BUDGET/IMPACT:

None

 

RECOMMENDED ACTION:

Recommended action

Motion to approve and authorize the Chairman and Clerk to repeal the originally approved WME-093-O and execute the Amended Water Main Extension Connection Agreement WME-093-O.