File #: 2021-2797   
Type: Consent Status: Agenda Ready
File created: 4/14/2021 Meeting Body Board of County Commissioners
On agenda: 5/4/2021 Final action:
Title: Request Approval of Task Order for Pre-Qualified Contractors for Miscellaneous Maintenance for Roads, Right-of-Ways, and Stormwater Management Facilities: 17Q-087-TO-41, DRA 7352 Major Maintenance Project - Hartman Civil Construction Co., Inc. - Ocala, FL (Budget Impact - Neutral; expenditure of $57,546 as approved in the FY 20/21 budget)
Attachments: 1. TO-41 AGN CNT, 2. TO-41 EC Misc Road ROW + SW Mgt (Hartman) ORIGINAL, 3. TO-41 Map

 

SUBJECT:

Title

Request Approval of Task Order for Pre-Qualified Contractors for Miscellaneous Maintenance for Roads, Right-of-Ways, and Stormwater Management Facilities: 17Q-087-TO-41, DRA 7352 Major Maintenance Project - Hartman Civil Construction Co., Inc. - Ocala, FL (Budget Impact - Neutral; expenditure of $57,546 as approved in the FY 20/21 budget)

Body

 

INITIATOR:

DEPARTMENT:

Susan Olsen, Director

Procurement Services

 

DESCRIPTION/BACKGROUND:

On behalf of the Office of the County Engineer (OCE), a Request for Qualifications (RFQ) was advertised for firms to provide repair and maintenance services for roads, right-of-ways, and stormwater facilities. On August 1, 2017, the Board contracted with five (5) firms to be Pre-Qualified contractors for various projects under this Agreement. A Task Order request was issued in March for repair in a drainage retention area (DRA). The work includes a sinkhole repair in a DRA consisting of standard clearing and grubbing, excavation, placing and compacting fill, erosion repair clearing and grubbing, and sodding. Tracy Straub, County Engineer, is recommending approval of the Task Order to Hartman Civil Construction, Co., Inc., the lowest Pre-Qualified Bidder, as shown in the tabulation below:

 

CONTRACTOR NAME - City

BID

Hartman Civil Construction - Ocala

$57,546.00

Art Walker Construction - Ocala

$77,299.99

 

Attached for review is the Task Order Amendment draft; pending approval at today’s meeting, it will be sent to the contractor for signature and upon return, will be routed for same by the County Attorney, Clerk, and Chairman.

 

BUDGET/IMPACT:

Neutral; expenditure of $57,546. Up to ten percent (10%) contingency can be added to the Purchase Order per the Procurement Manual.

 

RECOMMENDED ACTION:

Recommended action

Motion to approve recommendation and allow staff to issue the Task Order Amendment and upon approval by Legal, authorize the Chairman to execute same with Hartman Civil Construction, Co., Inc., under 17Q-087-TO-41.