SUBJECT:
Title
Request Approval of Short Water Line Extension Program Resolution to Support SWL-039 (Applicant - Holiday Builders, Inc.) (Budget Impact - None)
Body
INITIATOR: |
DEPARTMENT: |
Jody Kirkman, P.E., Utilities Director |
Utilities |
DESCRIPTION/BACKGROUND:
On August 17, 2021, the Board approved $5 million for the development and executions of a Short Water Line Extension Program (Program) providing subsidies for qualified applicants. On October 18, 2022, the Board approved Ordinance 22-43, which among other things, establishes the basic requirements for the Program. Property owners must apply and be qualified for the Program, which will include support of a future water main construction project when the owner’s property is within fifty (50) to five-hundred (500) feet of water main.
Marion County Utilities (MCU) verified parcel numbers 8010-0864-04 for participation in the Program, shown within the Resolution on Exhibit A - Application for the Short Water Line Extension Program. The project is designed to meet only the permitted parcel’s code compliance requirement with the project; a pending ARPA project within Marion Oaks Units 7 and 10 will complete this area’s water main construction in the coming months. This project provides for six (6) benefitting parcels and total project costs are shown within the Resolution on Exhibit C, based on MCU’s current bid pricing. When the pro rata share cost is derived for each parcel located within the discrete geographical area, each of the six (6) owners will pay the pro rata share of $4,857.75 as the actual cost paid by MCU under the bid, flagged on each served parcel.
BUDGET/IMPACT:
None; Project cost is $29,146, plus 10% contingency in accordance with the Procurement Manual. Funding is from FF449536-563102 with project code UTCEXT001
RECOMMENDED ACTION:
Recommended action
Motion to approve and authorize the Chairman and Clerk to execute the Short Water Line Extension Program Resolution and issue a purchase order for T&C Underground under 22P-146.
end