File #: 2024-14384   
Type: New Business Status: Agenda Ready
File created: 3/1/2024 Meeting Body Development Review Committee
On agenda: 3/4/2024 Final action:
Title: Aurora Oaks Phase 1 (aka: Calibrex) - Waiver Request to Improvement Plan in Review Project #2023040027 #30290 Parcel #35460-012-01 Tillman & Associates Engineering LDC 6.12.11. - Turn lanes CODE states Turn lanes shall be required as warranted by the project's Traffic Impact Analysis and in accordance with FDOT or as approved by the County Engineer. In addition, turn lanes shall be considered any time an unsafe condition exists or will be created. The cost of construction of such lanes shall be the responsibility of the developer. Additional right-of-way may be required and shall be dedicated by the developer and shown on the Improvement Plans and Final Plat. Any off-site improvement designs shall be submitted as an Improvement Plan application. APPLICANT requests waiver to receive Aurora Oaks Phase 1 Improvement Plan approval prior to the Offsite SW 59th Street/SW 60th Ave turn lane improvement plan approval. The off-site turn lane will be constructed prior to first CO w...
Attachments: 1. 6.2 Aurora Oaks Phase 1 (Fka Calibrex) - Waiver Request to Improvement Plan in Review - 30290_

 

SUBJECT:

Title

Aurora Oaks Phase 1 (aka: Calibrex) - Waiver Request to Improvement Plan in Review

Project #2023040027     #30290     Parcel #35460-012-01    

Tillman & Associates Engineering

 

LDC 6.12.11. - Turn lanes

CODE states Turn lanes shall be required as warranted by the project's Traffic Impact Analysis and in accordance with FDOT or as approved by the County Engineer. In addition, turn lanes shall be considered any time an unsafe condition exists or will be created. The cost of construction of such lanes shall be the responsibility of the developer. Additional right-of-way may be required and shall be dedicated by the developer and shown on the Improvement Plans and Final Plat. Any off-site improvement designs shall be submitted as an Improvement Plan application.

APPLICANT requests waiver to receive Aurora Oaks Phase 1 Improvement Plan approval prior to the Offsite SW 59th Street/SW 60th Ave turn lane improvement plan approval. The off-site turn lane will be constructed prior to first CO within Aurora Oaks Phase 1. All other traffic comments have been addressed.

Body

 

 

end